The operation of the ball mill is in order

  Ball mills buy home, although there is an instruction manual, but before watching, let's take a look at the order of the operation to summarize you.

  (1) Preparation before the ball mill starts:

  1. Check if someone in the dangerous place.

  2. Check if the lubricant of each lubrication point is appropriate, and it is added.

  3. Check if the steel ball filling rate in the ball mill meets the requirements.

  4, check if the abrasive liner bolt, the grinding head is loose and reliably tightened with the bolt and the barrel connection bolt.

  5. Fix the inlet cover reliably.

  6. Check the phenomenon in the barrel bolt hole and the in-hole, etc., and exclude it.

  7. When the first trial operation or long-term stop is started again, the hollow bearing should first pour a small amount of lubricating oil on both ends, and use artificial mill mill, or "point" to rotate one week, confirm that there is no abnormal phenomenon.

  8, and contact the job position before and after obtaining the signal that allows the start-up signal to start the grinding machine.

  (2) The order of ball mill starting:

  1, start powder output equipment.

  2, start the ball mill.

  3, start the feeder.

  (3) The order of ball mill is stopped:

  1. Stop the feeder.

  2, stop the ball mill. Long-term parking should take the steel ball and material blood.

  3, the conveyor continues to run until the machine is discharged, and then stops.