Tell you a simple method of calculating the ball grinder steel ball

  Today, share a simple method of calculating the ball grinding steel ball. Ball mill ball consumption is one of the important components of mineral cost. More accurately determine the ball consumption during the mill, and makes timely supplement, which is important to obtain a good grinding effect on the ball mill. The so-called grinding ball consumption is generally referred to in the process of grinding the ore, which is not recovered in the grinding product in the abrasive ore. It should be regarded as the ball consumed by the mill.

  Ball consumption is usually expressed in kg / t (primary mine). [Example] Some factory 1500mm × 3000mm ball mill is initially installed 10T, and the parking inspection has been treated with a total of 5000T after 3 months. It will be cleaned up in the machine.

  With a 6T ball, the mill grinder is 1.3 (kg / t) to maintain the ballual balance in the ball mill, and should be added to the 1.3kg ball according to each grinding LT ore. As for more than big balls, each adds, due to the wear of the ball is a complex process, usually simply supplement one or two larger balls, and regard the ball as a big ball. Due to the different ore properties, milling conditions, the material of the mineral conditions, the material is different, so they do their best to make reasonable supplements, do not lose, ensure that the ball mill is in a good working condition.